Projects

11 posts

Speciality Projects

This project required a few months of design to remove Spray Booms from a two-story building. The drawing below shows the design criteria and removal of the Spray Booms. There was design of equipment and platforms.

Bridge Jacking

Bridge Jacking

Jacking bridge sections and LRT sections are projects we have done for a long time. The LRT section weighs 1200 ton. This drawing is for lifting the LRT sections. Jacking Anthony Henday and Whitemud bridge. Bridge weighs 600 ton. This bridge was designed for an off ramp. Drawing below.

Conveyer Launcher Project1

Conveyer Launcher Project

This project was a complete redesign of our standard jack and slide systems. The tight confinement of the vessel left no room for sliding equipment. Therefore, all equipment placement and connections had to be outside of the vessel. The Launcher design accommodated this requirement to build and launch sections into […]

Ship Gantry System

Gantry Systems

Formula/Bradley Engineering has designed gantry systems for multiple applications. One of the applications that was a challenge and required a different design was for a drilling ship. Many other factors come into the design such as movement of the ship and location and amount of support locations. The design was […]

Wash Water Heater Vessel

Wash Water Heater Vessel

This vessel was small but it was located in a very difficult location for removal. This vessel was vertical, standing over two floors. The second floor had an opening for the vessel to be vertical and the vessel was attached to a stack that projected through the roof around 120 […]

Tower Jack And Slide

Tower Jack and Slide

Jack and Slide of this tower placed a lot of stress on the sliding equipment. The vessel was 30’-0” in diameter and 340’-0” LG. The vessel weighed in at 1000 Ton. Formula/Bradley supplied services for Hydro and Jack & Slide of the vessel which weighed full of water at 15,000,000 […]

Concrete Stack Removal

Concrete Stack Removal Demolition

This project entailed a Concrete Stack in a permanent structure. This concrete stack was a one-piece design and too large to remove without cutting an opening in the building. Also, to remove the Stack from the building would involve very large cranes on the exterior of the building, cost was […]

Prill Tower

Prill Tower Removal Demolition

This project was very interesting, each floor of the tower had to be removed in sections. These sections had to meet the loads for a crane chart of a Liebherr LTM 1250-5.1. There were five floors to be removed at 215’-0” in the air. Demolition is always precarious; weights of […]